4154 Barry Co Bridge Intermediate Cap Pour

 











Lee arrived at 12:47 to pour Bent 2 Cap, First truck arrived at 1:10, Plant was running behind. Lee tested concrete; Air 3.5%, had to add air second test 7%, Slump 4-1/2" and Temp 56°. he made three cylinders and pour began.














Next item to do will be placing Rip Rap and building pad for Crane to set beams when ready.

Comments