BRO-B005 (19)_Barry Co. Bridge Replacement FR 2040
I arrived at 11:15, Pump truck arrived at 11:30. First concrete truck arrived at 11:52, I tested concrete and started the pour foe Bent 2 Wall.
Concrete tested at 5.2% on Air, 2-3/4" on Slump and Temp was 60°, Made three cylinders.
Pour went good, finished around 1:15. Talked with the contractor and next Pour will be next Thursday.
Concrete tested at 5.2% on Air, 2-3/4" on Slump and Temp was 60°, Made three cylinders.
Pour went good, finished around 1:15. Talked with the contractor and next Pour will be next Thursday.