BRO-B005 (19)_Barry Co. Bridge Replacement FR 2040

Image
I arrived at 11:15, Pump truck arrived at 11:30. First concrete truck arrived at 11:52, I tested concrete and started the pour foe Bent 2 Wall. Concrete tested at 5.2% on Air, 2-3/4" on Slump and Temp was 60°, Made three cylinders. Pour went good, finished around 1:15. Talked with the contractor and next Pour will be next Thursday.  

BRO-B005 (19) Barry Co. Bridge FR 2040

Image
  Onsite to check Pile location for Bent 1 & 2.

BRO-B005 (19) Barry Co. Bridge FR 2040

BRO-B005 (19) Barry Co. Bridge Replacement

Image
  Decker was onsite to drive piling for all Bents. Intermediate bent still needing to be set. Finish Bent 1 pile, Hit rock early. Moving to Bent 2 to set pile. Set Bent 2 pile. Finished Bent 2 and seemed to hit rock early on all pile but all drove good.

BRO-B005 (19)_Barry Co. Bridge Replacement FR 2040

Image
Contractor was working on Clearing and Grubbing for all Bent Locations