Placing black beauty Continue to place black beauty on deck First coat completed will continue with 2nd coat tomorrow morning Placing riprap around end bents
I Arrived at 7:15 am, contractor had started placing post on bridge. Next will start hanging Thrie Beam on post. Next will have to build up Approaches to install the rest of the Guardrail
I arrived onsite at 11:00 am to pour wingwalls, First truck arrived at 11:14 am. I tested concrete; Air 5%, Slump 3" and Temp 60°, made three cylinders and pour began. Next will be installing Guardrail.
Contractor has started setting box beams Trucks showed and contractor started to install Continue to set box beams in place Finished setting beams and shimming
Arrived onsite at 7:00 am contractor was placing bearing pad and joint filler. First beam arrived at 8:47 am, crane hooker up to it and started to lift to find out that the beams where heavier than told. They was able to set six beams with this crane but will have to bring a bigger crane to set the other six. Crane conpamy will let Contractor know when they will have another crane onsite and let us know.